Implementing Pradhan Mantri Awas Yojana-Urban (PMAY-U) under “Housing for All” Mission since June, 2015
GOVERNMENT OF INDIA
MINISTRY OF HOUSING AND URBAN AFFAIRS
LOK SABHA
UNSTARRED QUESTION NO. 85
TO BE ANSWERED ON FEBRUARY 02, 2023
HOUSING FOR ALL
NO. 85.SHRI A. RAJA:
Will the Minister of HOUSING AND URBAN AFFAIRS be pleased to state:
a) the total number of houses constructed during the period 2019 to 2022 under the scheme ‘Housing for All’ in the country, State/UT-wise;
(b)the funds earmarked for this purpose, State/UT-wise;
(c)whether the target for sanctioning of construction of affordable housing under the scheme would be achieved as per the proposed deadline of 2022;
(d)if not, whether the time would be extended for the same and if so, the details thereof; and
(e)the measures taken by the Government to expedite the pending projects under the said scheme?
ANSWER
THE MINISTER OF STATE IN THE MINISTRY OF HOUSING AND URBAN AFFAIRS
(SHRI KAUSHAL KISHORE)
(a)&(b)MinistryofHousingandUrbanAffairshasbeen implementing Pradhan Mantri Awas Yojana-Urban (PMAY-U) under “Housing for All” Mission since June, 2015 giving Central assistance to implementing agencies through States/ Union Territories (UTs) for providing all-weather pucca houses with basic civic amenities to all eligible urban beneficiaries through four verticals i.e. Beneficiary-led individual house construction/ enhancement (BLC); Affordable Housing in Partnership (AHP); ‘In-situ’ Slum Redevelopment (ISSR); and Credit Linked Subsidy Scheme (CLSS). State/ UT-wise details of number of houses sanctioned and Central assistance approved during the period 2019 to 2022 under PMAY-U are at Annexure.
(c) to (e) PMAY-U is a demand driven scheme and Government of India has not fixed any target for construction of houses. States/ UTs have undertaken demand survey under PMAY-U for assessing actual demand of housing and reported a demand of 112.24 lakh houses. Based on the project proposals submitted by States/ UTs as on 31.03.2022, a total of 122.69 lakh houses were sanctioned. Of the sanctioned houses, 107.55 lakh have been grounded for construction; of which 68.02 lakh are completed/ delivered to beneficiaries as on 23.01.2023.
Completion of projects generally takes 12-36 months in different verticals of the scheme. The scheme period has been extended up to 31.12.2024 with existing funding pattern and implementation methodology to complete the houses sanctioned till 31.03.2022.
States/ UTs have been advised to expedite the construction of sanctioned houses so that all houses are completed within the stipulated timeline as per Detailed Project Reports. Ministry regularly monitors progress of the scheme through periodic review meetings, video-conferences and field visits.
Annexure referred in reply to LS UQ No. 85 due for 02.02.2023
State/UT- wise details of number of houses sanctioned and Central Assistance approved during last three years (FY 2019-20 to 2021-22) under PMAY-U
As on 23.01.2023
S. No.
Name of the State/ UT
Details of no. of houses sanctioned during last three years (FY 2019-20 to FY 2021-22)
Central assistance approved during last three years
नोट :- हमारे वेबसाइट indiangovtscheme.com पर ऐसी जानकारी रोजाना आती रहती है, तो आप ऐसी ही सरकारी योजनाओं की जानकारी पाने के लिए हमारे वेबसाइट indiangovtscheme.comसे जुड़े रहे।
Implementing Pradhan Mantri Awas Yojana – Urban for Poor
GOVERNMENT OF INDIA
MINISTRY OF HOUSING AND URBAN AFFAIRS
LOK SABHA
UNSTARRED QUESTION NO. 1604
TO BE ANSWERED ON DECEMBER 15, 2022
AFFORDABLE HOUSING TO URBAN POOR
NO. 1604. SHRI THIRUMAAVALAVAN THOL:
Will the Minister of HOUSING AND URBAN AFFAIRS be pleased to state:
(a)whether the Pradhan Mantri Awas Yojana (PMAY) aimed to provide affordable housing to the urban poor with a target of building two crore affordable houses by 31 March, 2022;
(b)if so, the status report on this initiative;
(c)the details of homelessness, in percentage terms eradicated due to this initiative; and
(d)whether the Government has any proposal to increase the unit cost under the PMAY-Urban and if so, the details thereof?
ANSWER
THE MINISTER OF STATE IN THE MINISTRY OF HOUSING AND URBAN AFFAIRS
(SHRI KAUSHAL KISHORE)
(a)to (c): The Ministry of Housing and Urban Affairs (MoHUA) is implementing Pradhan Mantri Awas Yojana – Urban (PMAY-U), Housing for All since 2015 to provide pucca house with basic amenities to the eligible urban families including homeless across the country. As per PMAY-U Scheme guidelines, States/Union Territories (UTs) were mandated to conduct demand survey through their respective Urban Local Bodies with the vision of ‘Housing for All’ following saturation approach. Against the validated demand of 1.12 crore houses, as on 28.11.2022, 1.20 crore houses have been sanctioned by the Ministry based on the project proposals submitted by States/UTs, out of which 1.06 crore have been grounded and more than 64 lakh have been completed/delivered to the beneficiaries. The Scheme has been extended till 31st December 2024 for completion of all the houses sanctioned under the Scheme. The State/UT-wise details of houses sanctioned, grounded and completed under the scheme are at Annexure-I.
(d): Government of India is sanctioning the proposals based on the Detailed Project Reports (DPRs) along with project cost prepared by the implementing agencies of States/UTs. Government of India is providing its fixed share as Central Assistance of ₹1.0 lakh under In-Situ Slum Redevelopment (ISSR), ₹1.5 lakh for Affordable Housing in Partnership (AHP) and Beneficiary Led Individual Construction or Enhancement (BLC) verticals of PMAY-U. Under Credit Linked Subsidy Scheme (CLSS) vertical of PMAY-U, an interest subsidy at the rate of 6.5% which amounts upto ₹ 2.67 lakh per house is provided for beneficiaries of Economically Weaker Sections (EWS) and Lower Income Group (LIG) category. The remaining cost of the house as per DPR is shared by States/UTs/Urban Local Bodies (ULBs)/Beneficiaries. There is no proposal to increase the Central Assistance with this Ministry.
Annexure-I referred in reply to LS USQ No. 1604 due for answer on 15.12.2022 State/UT-wise details of houses sanctioned, grounded for construction and completed under PMAY-U
S. No.
States/UTs
Houses sanctioned (Nos.)
Houses grounded (Nos.)
Houses completed (Nos.)
1
Andhra Pradesh
20,74,770
19,08,828
6,32,330
2
Bihar
3,27,321
3,09,599
98,936
3
Chhattisgarh
3,06,043
2,56,429
1,55,393
4
Goa
3,150
2,995
2,814
5
Gujarat
10,60,383
9,20,579
7,18,785
6
Haryana
1,66,762
91,400
55,278
7
Himachal Pradesh
13,249
12,826
8,521
8
Jharkhand
2,34,369
2,14,293
1,16,226
9
Karnataka
7,06,352
5,98,612
2,79,796
10
Kerala
1,66,661
1,32,793
1,04,730
11
Madhya Pradesh
9,60,261
8,95,900
5,55,956
12
Maharashtra
15,11,619
9,80,974
6,58,312
13
Odisha
2,13,846
1,66,548
1,15,389
14
Punjab
1,32,916
1,05,392
58,239
15
Rajasthan
2,76,766
1,88,358
1,37,716
16
Tamil Nadu
6,88,862
6,30,133
4,81,061
17
Telangana
2,49,467
2,39,424
2,11,992
18
Uttar Pradesh
16,89,827
15,18,085
11,84,821
19
Uttarakhand
62,763
42,546
25,268
20
West Bengal
6,91,150
5,11,989
2,99,553
Sub-total (States)
115,36,537
97,27,703
59,01,116
21
Arunachal Pradesh
9,002
8,526
3,900
22
Assam
1,61,478
1,56,007
63,999
23
Manipur
56,037
46,911
9,252
24
Meghalaya
4,759
3,776
1,098
25
Mizoram
40,756
38,340
6,009
26
Nagaland
32,335
32,100
10,849
27
Sikkim
704
579
183
28
Tripura
94,162
81,542
62,595
Sub-total (N.E. States)
3,99,233
3,67,781
1,57,885
29
A&N Islands
378
377
45
30
Chandigarh
1,271
1,197
1,126
31
D&NH and D&D
10,481
9,565
7,371
32
Delhi
30,195
28,710
27,308
33
J&K
49,146
47,281
16,147
34
Ladakh
1,366
1,074
643
35
Lakshadweep
–
–
–
36
Puducherry
16,394
16,031
7,423
Sub-total (UTs)
1,09,231
1,04,235
60,063
Total
120.45 Lakh**
106.01 Lakh*
64.60 Lakh*
* Includes completed (3.41 lakh)/ grounded (4.01 lakh) houses of JnNURM during mission period.
** Out of 122.69 lakh houses sanctioned as on 31.3.2022, 2.24 lakh non-starter houses have been curtailed by some States against which States to put up new proposals under BLC vertical of PMAY-U.
नोट :- हमारे वेबसाइट indiangovtscheme.com पर ऐसी जानकारी रोजाना आती रहती है, तो आप ऐसी ही सरकारी योजनाओं की जानकारी पाने के लिए हमारे वेबसाइट indiangovtscheme.comसे जुड़े रहे।
Implementing Pradhan Mantri Awas Yojana-Urban (PMAY-U) – ‘Housing for All’ Mission, since 25.06.2015
GOVERNMENT OF INDIA
MINISTRY OF HOUSING AND URBAN AFFAIRS
LOK SABHA
UNSTARRED QUESTION NO. 2999
TO BE ANSWERED ON AUGUST 04, 2022
PRADHAN MANTRI AWAS YOJANA
NO. 2999.SHRI NATARAJAN P.R.
Will the Minister of Housing and Urban Affairs be pleased to state:
(a)whether the Government is having any statistics on providing house for all under Pradhan Mantri Awas Yojana (PMAY);
(b)if so, the details of number of houses sanctioned/ completed/ grounded and allotted to beneficiaries under PMAY during the last four years and the current year;
(c)the details of funds/provisions made and utilised during the said period, year and State-wise along with Central assistance and State share;
(d)the details of number of housing projects are under construction; and
(e)the time line fixed for early completion of pending projects?
ANSWER
THE MINISTER OF STATE IN THE MINISTRY OF HOUSING AND URBAN AFFAIRS
(SHRI KAUSHAL KISHORE)
(a) & (b): Yes, Sir. Ministry of Housing and Urban Affairs is implementing Pradhan Mantri Awas Yojana-Urban (PMAY-U) – ‘Housing for All’ Mission, since 25.06.2015 for giving Central assistance to States/ Union Territories (UTs) for providing all-weather pucca houses to all eligible urban beneficiaries. Based on the project proposals submitted by States/ UTs, a total of 122.69 lakh houses have been sanctioned during the Mission period i.e. till 31 March 2022.
Against the sanctioned houses, 102.23 lakh have been grounded for construction; of which 61.50 lakh are completed/ delivered to beneficiaries.
Under PMAY-U, during the last four years and current year, a total of 89,90,838 houses have been sanctioned, 78,92,361 have been grounded for construction, 54,08,086 have been completed and 48,66,306 have been allotted/occupied by beneficiaries.
(c): State/UT-wise and year-wise details of Central assistance released and utilised during last four years and current year (FY 2018- 2023) under PMAY-U are at Annexure-I.
State/UT-wise and year-wise details of Central assistance and State share approved during last four years and current year (FY 2018- 2023) under PMAY-U are at Annexure-II.
(d) & (e): State/UT-wise details of number of projects along with houses which are presently under construction under PMAY-U are at Annexure-III.
Completion of projects generally takes 12-36 months in different verticals of the Scheme. Out of the total 122.69 lakh sanctioned houses, around 41 lakh houses have been sanctioned in the last two years. States/ UTs have been advised to expedite the construction of sanctioned houses so that all houses are completed within the stipulated timeline as per Detailed Project Reports.
Annexure I referred in reply to LSU Q No. 2999 due for 04-08-2022
State/UT-wise details of Central Assistance released and utilized during each of the last four years and current year (FY 2018-2023) under PMAY-U
Sl. No.
State/UT
Central Assistance Released (₹ in Cr.)
Central Assistance Utilised (₹ in Cr.)*
2018-19
2019-20
2020-21
2021-22
2022-23
2018-19
2019-20
2020-21
2021-22
2022-23
1
A&N Island (UT)
0.05
0.17
0.46
1.06
–
0.05
–
0.46
1.06
–
2
Andhra Pradesh
3,465
919
2,419
2,475
1,664
2,569
1,566
3,166
3,991
–
3
Arunachal Pradesh
11
21
8.57
28
–
21
0.65
7.53
56
–
4
Assam
15
494
126
180
–
8
245
660
131
74
5
Bihar
505
528
572
93
–
84
206
1,095
566
190
6
Chandigarh (UT)
3.42
8.24
9.18
3.45
–
3.42
8.24
9.18
3.45
–
7
Chhattisgarh
419
725
690
381
–
101
742
1,108
611
–
8
UT of DNH & DD
28
36
46
26
–
24
33
46
45
–
9
Delhi (NCR)
230
144
145
45
–
230
144
145
45
–
10
Goa
9.35
10
37
9.17
–
8.99
10
37
9.19
–
11
Gujarat
3,487
2,254
3,242
4,193
–
2,973
2,225
3,700
4,470
617
12
Haryana
369
248
290
173
–
191
187
295
329
–
13
Himachal Pradesh
25
30
33
46
–
5.37
20
51
56
12
14
J&K (UT)
34
100
132
44
–
4.76
87
35
123
–
15
Jharkhand
419
331
535
260
–
617
528
421
226
65
16
Karnataka
729
702
1,142
530
–
798
713
2,096
1,084
–
17
Kerala
661
266
174
372
13
207
275
210
780
–
18
Ladakh (UT)
1.79
–
0.43
4.46
–
0.49
–
0.43
7.35
–
19
Lakshadweep (UT)
–
–
–
–
–
–
–
–
–
–
20
Madhya Pradesh
2,723
1,045
2,412
1,978
432
1,159
1,297
5,375
3,181
280
21
Maharashtra
2,863
2,405
3,943
3,358
–
2,603
2,344
3,606
3,425
–
22
Manipur
12
65
100
0.13
–
1.22
0.10
184
4.61
303
23
Meghalaya
0.99
0.64
1.30
17
–
0.99
4.40
1.20
11
5.17
24
Mizoram
34
7.89
72
14
–
5.74
74
31
14
–
25
Nagaland
65
14
106
34
–
1.44
15
8.19
128
–
26
Odisha
411
321
387
328
–
499
327
427
284
–
27
Puducherry (UT)
15
51
37
17
–
8.66
33
73
11
–
28
Punjab
182
188
507
253
–
148
188
432
401
–
29
Rajasthan
398
601
789
996
–
454
557
882
724
125
30
Sikkim
1.80
0.38
1.57
1.35
–
0.18
0.38
1.57
1.35
–
31
Tamil Nadu
1,409
1,942
1,627
1,570
–
483
2,841
2,478
2,227
353
32
Telangana
342
385
777
298
–
1,378
409
838
298
–
33
Tripura
151
166
234
62
–
437
159
29
291
144
34
Uttar Pradesh
4,626
4,046
4,913
3,943
–
1,790
6,381
4,811
4,170
1,039
35
Uttarakhand
80
80
161
89
–
71
159
111
109
14
36
West Bengal
1,294
931
1,607
421
–
1,547
1,025
1,272
1,410
270
Grand Total :-
25,019
19,068
27,276
22,243
2,110
18,435
22,802
33,641
29,229
3,486
* Includes funds utilized against Central Assistance released preceding years of last three years and current year
नोट :- हमारे वेबसाइट indiangovtscheme.com पर ऐसी जानकारी रोजाना आती रहती है, तो आप ऐसी ही सरकारी योजनाओं की जानकारी पाने के लिए हमारे वेबसाइट indiangovtscheme.comसे जुड़े रहे।
Implementing Pradhan Mantri Awas Yojana-Urban (PMAY-U) – ‘Housing for All’ Mission, since 25.06.2015
GOVERNMENT OF INDIA
MINISTRY OF HOUSING AND URBAN AFFAIRS
LOK SABHA
UNSTARRED QUESTION NO.758
TO BE ANSWERED ON JULY 21, 2022
IMPLEMENTATION OF PMAY-U
NO. 758. SHRI VIJAYAKUMAR (ALIAS) VIJAY VASANTH:
Will the Minister of Housing and Urban Affairs be pleased to state:
(a)the present status of implementation of Pradhan Mantri Awas Yojana- Urban (PMAY-U) and the number of houses constructed during the last three years and the amount spent for the same, year/ State-wise;
(b)whether the Government has any proposal to extend PMAY till March, 2024;
(c)if so, the details thereof and the fresh targets, if any, fixed for the same; and
(d)if not, the reasons therefor?
ANSWER
THE MINISTER OF STATE IN THE MINISTRY OF HOUSING AND URBAN AFFAIRS
(SHRI KAUSHAL KISHORE)
(a) to (d): Ministry of Housing and Urban Affairs is implementing Pradhan Mantri Awas Yojana-Urban (PMAY-U) – ‘Housing for All’ Mission, since 25.06.2015 for giving Central assistance to States/ Union Territories (UTs) for providing all-weather pucca houses to all eligible urban beneficiaries. Based on the project proposals submitted by States/ UTs, a total of 122.69 lakh houses have been sanctioned during the Mission period i.e. till 31 March 2022.
Against the sanctioned houses, 101.94 lakh have been grounded for construction; of which 61.15 lakh are completed/ delivered to beneficiaries. Central assistance of Rs. 2,03,427 crore has been approved; out of which Rs. 1,20,130 crore have been released. State- wise and Year-wise details of number of houses constructed and Central assistance released during last three years are at Annexure.
A proposal seeking extension of the Mission upto March 2024, to complete all houses sanctioned under the scheme upto 31 March 2022 without changing the funding pattern and implementation methodology, is under consideration. Meanwhile, an interim extension of 6 months for all verticals except Credit Linked Subsidy Scheme has been granted.