Houses sanctioned and completed under Pradhan Mantri Awas Yojana – Urban (PMAY-U)
GOVERNMENT OF INDIA
MINISTRY OF HOUSING AND URBAN AFFAIRS
LOK SABHA
UNSTARRED QUESTION NO. 2056
TO BE ANSWERED ON DECEMBER 11, 2025
STATUS OF HOUSES COMPLETED UNDER PMAY-U
NO. 2056. MR PATHAN YUSUF:
Will the Minister of HOUSING AND URBAN AFFAIRS be pleased to state:
(a) the details and the number of houses sanctioned and completed under Pradhan Mantri Awas Yojana – Urban (PMAY-U) since its inception, year and component-wise;
(b) the details and the total number of houses completed under PMAY-U which are currently occupied by beneficiaries since its inception, year and component-wise; and

(c) the details and the number of houses completed under PMAY-U which remain unoccupied by beneficiaries since its inception, year and component-wise along with the reasons therefor?
ANSWER
THE MINISTER OF STATE IN THE MINISTRY OF HOUSING AND URBAN AFFAIRS
(SHRI TOKHAN SAHU)
(a) to (c): Ministry of Housing and Urban Affairs (MoHUA) has been implementing Pradhan Mantri Awas Yojana – Urban (PMAY-U) since 25.06.2015 with an aim to provide all weather pucca houses with basic civic amenities to eligible urban beneficiaries across the country. The scheme is implemented through four verticals i.e., Beneficiary Led Construction (BLC), Affordable Housing in Partnership (AHP), In-Situ Slum Redevelopment (ISSR) and Credit Linked Subsidy Scheme (CLSS). The year and component-wise details of houses sanctioned, completed and occupied by the beneficiaries under PMAY-U since its inception is at Annexure.
The scheme period, which was earlier up to 31.03.2022, has further been extended up to 31.12.2025 to complete sanctioned houses without changing the funding pattern and implementation methodology. The occupancy of AHP/ISSR houses is an important concern raised with States/Union Territories (UTs) during review meetings. The reasons of unoccupancy include incomplete basic infrastructure such as water, roads and electricity, migration or unwillingness to relocate from existing livelihoods and social networks, financial constraints in contributing beneficiary share, delays in documentation and allotment by implementing agencies. The Ministry conducts regular review meetings with States/UTs to complete the remaining houses and ensure occupancy within the stipulated timeframe. The States/UTs have been advised to improve occupancy of houses under AHP/ISSR verticals of PMAY-U by providing civic infrastructure and ensuring allotment to beneficiaries on priority.
Further, based on the learnings from the experiences of implementation of PMAY-U, MoHUA has revamped the scheme and launched PMAY-U 2.0 ‘Housing for All’ Mission with effect from 01.09.2024 for implementation in urban areas across the country to support 1 crore additional eligible beneficiaries in next five years. PMAY-U 2.0 is implemented through four verticals i.e., Beneficiary Led Construction (BLC), Affordable Housing in Partnership (AHP), Affordable Rental Housing (ARH) and Interest Subsidy Scheme (ISS). As on date, 10.43 lakh houses have been sanctioned under PMAY-U 2.0.
Annexure referred in reply to LS USQ No. 2056 due for answer on 11.12.2025 Year and component-wise details of houses sanctioned, completed and occupied by the beneficiaries under PMAY-U since its inception
|
FY |
Overall Houses under Mission | |||||
| BLC | AHP/ISSR | CLSS | ||||
|
Sanctioned |
Completed/ Occupied |
Sanctioned |
Completed |
Occupied |
Sanctioned/ Completed/ Occupied | |
| 2015-16 | 1,61,022 | 1,53,120 | 3,59,218 | 3,25,909 | 2,71,264 | 5,835 |
| 2016-17 | 4,68,821 | 4,31,133 | 1,42,332 | 1,11,695 | 76,043 | 22,607 |
| 2017-18 | 9,94,039 | 8,98,810 | 5,59,246 | 4,15,438 | 2,44,494 | 1,12,449 |
| 2018-19 | 14,05,834 | 12,40,116 | 3,99,634 | 2,76,954 | 1,80,823 | 4,27,004 |
| 2019-20 | 11,45,038 | 8,78,066 | 54,484 | 38,793 | 24,143 | 4,16,403 |
| 2020-21 | 8,73,179 | 5,63,829 | 69,242 | 36,040 | 15,792 | 6,05,751 |
| 2021-22 | 10,50,244 | 7,10,339 | 98,844 | 37,298 | 16,912 | 4,83,871 |
| 2022-23 | 4,90,984 | 3,33,930 | – | – | – | 4,30,300 |
| 2023-24 | 3,86,057 | 2,55,885 | – | – | – | – |
| Total | 69,75,218 | 54,65,228 | 16,83,000 | 15,84,141* | 13,20,452* | 25,04,220 |
* Includes completed (3.42 lakh) houses and occupied (4.90 lakh) houses of JnNURM during Mission period.