National Heritage City Development and Augmentation Yojna
(a) No, Sir. The National Heritage City Development and Augmentation Yojna (HRIDAY) is a central sector scheme and the funds are directly released to the cities.Out of the total sanctioned funds of Rs. 418.06 crore, an amount of Rs. 402.44 crore (96.26%) has been released.
(b) to (d) The details are attached as Annexure–A.
Annexure-A
Amritsar (Punjab)
S.
No.
|
Name of the Project |
Sanction Date |
Amount released (in crore) |
Progress
Status (as on
31.03.2019)
|
UC
Received
till 31.03.2019
(in crore)
|
1
|
Landscape Improvements and Historic Edge Delineation of the Rambagh Garden |
07.12.2015 | 1.71 | 95% progress |
1.71
|
2
|
Restoration & Adaptive Reuse of Rambagh Gate | 07.12.2015 | 3.28 | Completed |
0.95
|
3
|
Comprehensive road development and up-gradation of 21 major roads leading to Golden Temple |
10.10.2016 | 31.27 | Completed | 29.31 |
4
|
Reorganizing Connectivity and Linkages through Streetscape and Landscape improvement at GolBagh |
10.10.2016 | 4.99 | Completed |
3.79
|
5
|
Comprehensive Improvement of a mobility corridor along the outer and inner circular road |
10.10.2016 | 4.88 | Completed |
3.89
|
6
|
Revitalization and Infrastructure Development at 40 Khoo, or 40 Wells and Colonial Period Power House |
10.10.2016 | 8.36 | 65% progress |
5.39
|
7
|
Development of an Environmental Park at the UBDC Canal | 10.10.2016 | 1.14 | 70% progress |
0.78
|
8
|
Structural retrofitting and up-gradation of the historic fabric of the colonial period building of the DC Office |
10.10.2016 | 1.95 | 85% progress |
1.58
|
9
|
Up-gradation of the Maharaja Ranjit Singh Panorama | 10.10.2016 | 0.49 | Completed |
0.40
|
10 | Interpretative Signage in the City with Sensors | 14.10.2016 | 2.13 | 50% progress |
0.68
|
11 | Heritage lighting for proper illumination of various sites | 5.09.2018 | 1.99 | 90% progress |
0.79
|
12 |
Conservation of the historic gates and improvement in the Heritage Zone4 – Circular Road – Historic Connector |
22.10.2018 | 11.23 | 45% progress |
4.75
|
Total
|
73.57 | 54.02 |
Amaravati (Andhra Pradesh)
S.
No.
|
Name of the Project |
Sanction Date |
Amount released (in crore) |
Progress
Status (as on
31.03.2019)
|
UC
Received
till 31.03.2019
(in crore)
|
1
|
Up-gradation of Approach roads to Heritage Sites | 28.10.2015 | 10.01 | Completed | 12.15 |
2
|
Development of Heritage Walk | 28.10.2015 | 2.32 | Completed | |
3
|
Development of Amaravati Pond (NunegundamCheruvu) | 21.08.2018 | 4.27 | 60% progress |
1.82
|
Total
|
16.60 | 13.97 |
Ajmer (Rajasthan)
S.
No.
|
Name of the Project |
Sanction Date |
Amount released (in crore) |
Progress
Status (as on
31.03.2019)
|
UC
Received
till 31.03.2019
(in crore)
|
1
|
Development of Heritage Walk connecting Akbari Quila and Soniji ki Nasiya |
5.01.2016 | 4.41 | Completed |
2.93
|
2
|
Development of Jaipur Road Precinct | 4.07.2016 | 2.83 | Completed |
1.21
|
3
|
Development of Pushkar Heritage Walk | 4.07.2016 | 4.92 | Completed |
2.73
|
4
|
Development of Subhash Udyan | 4.07.2016 | 10.61 | Completed | 10.61 |
5
|
Annasagar Lakefront Up-gradation | 19.10.2016 | 9.35 | Completed |
7.80
|
6
|
Development of Vehicular Surface Parking at Longia Hospital, Ajmer |
1.02.2019 | 2.05 | Completed |
0.83
|
7
|
Development of Rail Museum at Ajmer | 14.01.2019 |
– *
|
25% progress |
–
|
Total
|
34.17 | 26.11 |
* being implemented from the savings of other projects.
Badami (Karnataka)
S. No. |
Name of the Project |
Sanction Date |
Amount released (in crore) |
Progress
Status (as on
31.03.2019)
|
UC
Received till 31.03.2019
(in crore)
|
1
|
Development of Sullage Treatment Plant in Takkote Village. (Replaced by underground drainage work) |
23.06.2016 |
0.42
|
Completed |
0.37
|
2
|
Zero Waste Management for Badami Town | 29.06.2016 |
2.42
|
Completed |
1.84
|
3
|
Integrated Development and Improvement of Arterial Road, Transportation Infrastructure, Parking and Road Signage |
29.06.2016 | 16.19 |
70%
progress
|
11.18 |
Total
|
19.03 | 13.39 |
Dwarka (Gujarat)
S.
No.
|
Name of the Project |
Sanction Date |
Amount released (in crore) |
Progress
Status (as on
31.03.2019)
|
UC
Received
till 31.03.2019
(in crore)
|
1
|
Vegetable market square | 4.07.2016 | 2.49 | Completed |
1.38
|
2
|
Sidheshwar Mahadev Precinct | 4.07.2016 | 2.54 | Completed |
1.41
|
3
|
Darshan Path – Teen Batti | 4.07.2016 | 1.41 | Completed |
1.10
|
4
|
Development of heritage zone 01 Dwarkadhish temple square | 14.10.2016 | 2.14 | Completed |
1.45
|
5
|
Development of heritage zone 04 Main Processional Street (Darshan Path) from Iskon Gate to Dwarkadhish temple |
14.10.2016 | 4.49 | Completed |
3.08
|
6
|
Development of Bet Dwaraka Darshan Circuit | 24.08.2017 | 10.69 |
40%
progress.
|
5.30
|
7
|
Revitalization of Vegetable Market, Brahma Kund, Hari Kund and Savitri Vav at Dwaraka |
24.12.2018 | 2.10 |
30%
progress
|
0.84
|
8
|
Installation of CCTV Cameras and Wi-Fi Systems in the identified Heritage Zones in Dwaraka |
27.02.2019 | 1.90 |
60%
progress
|
0.76
|
Total
|
27.76 | 15.32 |
Gaya (Bihar)
S.
No.
|
Name of the Project |
Sanction Date |
Amount released (in crore) |
Progress
Status (as on
31.03.2019)
|
UC
Received
till 31.03.2019
(in crore)
|
1
|
Development of Ghats and Sarovars at Gaya: Brahmsat and Baitarani Sarovar |
31.03.2016 | 5.86 |
75%
progress
|
4.69
|
2
|
Development of Ghat and Vishnupad temple complex | 29.12.2016 | 7.94 |
45%
progress
|
7.02
|
3
|
Development of Akshay Vat Complex (Zone-2) at Gaya | 29.12.2016 | 1.61 |
88%
progress
|
1.29
|
4
|
Development of Connecting pathway- Dungeshwari hill to Mahabodhi temple (Zone-6) at Bodh Gaya |
29.12.2016 | 7.60 |
70%
progress
|
7.36
|
5
|
Development of Sita Kund Temple Complex | 12.09.2018 | 5.99 |
80%
progress
|
3.21
|
6
|
Development of Pita Maheshwar Sarovar | 12.09.2018 | 1.95 |
80%
progress
|
0.99
|
7
|
Beautification and Development of Ram Kund, Ram Sagar, Godavari and Singra Sthan Sarovar |
18.02.2019 | 4.71 |
15%
progress
|
–
|
Total
|
35.66 | 24.56 |
Kancheepuram (Tamil Nadu)
S.
No
|
Name of the Project |
Sanction Date |
Amount released (in crore) |
Progress
Status (as on
31.03.2019)
|
UC
Received
till 31.03.2019
(in crore)
|
1
|
Development and Infrastructure Up-gradation around Ekambareswarar Temple |
17.02.2016 |
9.89 |
Completed |
8.40
|
2
|
Development and Infrastructure Up-gradation around Varadharaja Perumal Temple Zone. |
17.02.2016 | 7.63 | Completed |
6.66
|
3.
|
Development and Infrastructure Works Around Kamatchi Amman Temple |
10.10.2017 |
1.96 |
90% progress |
1.76
|
Total
|
19.48 | 16.82 |
Mathura (Uttar Pradesh)
S.
No.
|
Name of the Project |
Sanction Date |
Amount released (in crore) |
Progress
Status (as on
31.03.2019)
|
UC
Received
till 31.03.2019
(in crore)
|
1
|
Redevelopment and Revitalization of Vrindavan Parikrama Marg |
08.03.2016 |
7.68
|
Completed |
4.23
|
2
|
Krishna Janmabhoomi Precinct | 29.12.2016 |
5.20
|
90%
progress
|
3.32
|
3
|
Revitalization of the Historic Chatta Bazaar | 29.12.2016 |
2.46
|
70%
progress
|
2.46
|
4
|
Rejuvenation of the Historic Vishram Ghat | 29.12.2016 |
1.45
|
70%
progress
|
1.45
|
5
|
Façade Lighting at Potra Kund | 14.01.2019 |
4.96
|
90%
progress
|
1.59
|
6
|
Installation of CCTV Cameras at Krishna Janmsthan, Vrindavan Parikrama Marg and Vishram Ghat |
14.01.2019 |
-*
|
50%
progress
|
–
|
7
|
Beautification of Krishnapuri Tiraha | 14.01.2019 |
-*
|
50%
progress
|
–
|
8
|
Installation of Street Furniture etc. | 14.01.2019 |
-*
|
10%
progress
|
–
|
Total
|
21.75 | 13.05 |
* being implemented from the savings of other projects.
Puri (Odisha)
S.
No.
|
Name of the Project |
Sanction Date |
Amount released (in crore) |
Progress
status (as on
31.03.2019)
|
UC
Received
till 31.03.2019
(in crore)
|
1
|
Development of Landscape Garden by using treated water from waste water treatment plant at Banki Muhana |
31.03.2016 |
3.62
|
Completed |
3.62
|
2
|
Landscape development of Shri Jagannatha Ballabh Matha Garden |
10.10.2016 |
7.04
|
75% progress |
3.52
|
3
|
Landscape development etc. along the River Front Atharnala | 10.10.2016 |
1.54
|
65% progress |
1.54
|
4
|
Improvement and facades up-gradation of Bada Odiya Matha and Ganga Mata Matha |
10.10.2016 |
1.47
|
75% progress |
0.73
|
5
|
Revival of Pokharis, Ponds located in 7 Jagaghara | 10.10.2016 |
0.79
|
Completed |
0.79
|
6
|
Retrofitting of building facades along the Parikrama Marg (periphery) of Shri Jagannatha Temple |
10.10.2016 |
1.66
|
67% progress |
1.19
|
Total
|
16.12 | 11.39 |
Velankanni (Tamil Nadu)
S.
No.
|
Name of the Project |
Sanction Date |
Amount released (in crore) |
Progress
Status (as on
31.03.2019)
|
UC
Received
till 31.03.2019
(in crore)
|
1
|
Development of support infrastructure at Velankkanni | 21.12.2015 |
0.77
|
Completed |
0.17
|
2
|
Heritage linked infrastructure development of Three Delineated zones |
29.12.2016 |
9.60
|
Completed |
8.68
|
3.
|
Additional Heritage linked infrastructure development of Three Delineated zones |
16.11.2017 |
8.66
|
85%
progress
|
5.52
|
Total
|
19.03 | 14.37 |
Varanasi (Uttar Pradesh)
S.
No.
|
Name of the Project |
Sanction Date |
Amount released (in crore) |
Progress
Status (as on
31.03.2019)
|
UC
Received
till 31.03.2019
(in crore)
|
1
|
Construction of 10 approach Roads to various heritage sites | 01.06.2015 |
7.91
|
Completed |
7.48
|
#
|
Development of Dashashwamedh – Godowlia Culture Quarter. | 18.04.2016 |
0.19
|
Dropped |
0.15
|
2
|
Redevelopment of Town Hall as Heritage Centre | 18.04.2016 |
2.26
|
Completed |
2.25
|
3
|
Development of 24 Roads leading to various heritage sites | 13.04.2016 | 21.69 | Completed | 21.00 |
4
|
Development of Heritage precinct of Road Connecting Durgakund, Kurushetra Pokhra and AssiGhat |
29.06.2016 |
1.42
|
Completed |
1.08
|
5
|
Carrying out Heritage Artistic Paint Work | 23.08.2016 |
0.07
|
Completed |
0.03
|
6
|
Heritage Walk around Kabir Chaura and Piplani Katra | 14.10.2016 |
2.30
|
Completed |
2.30
|
7
|
Development of 86 heritage sites | 14.10.2016 | 11.97 | Completed |
9.40
|
8
|
Implementation of Heritage Sensitive Infrastructure for LED Street Lighting at Old Kashi Zone |
15.05.2017 | 21.20 | Completed | 10.60 |
9
|
Thematic Development of 10 Roads leading to Various Heritage Sites |
30.05.2017 |
5.47
|
80%
progress
|
2.40
|
10. | Façade Lighting for Historic monument of Town Hall and Durga Mandir |
06.02.2018 |
1.03
|
Completed |
0.82
|
11. | Installation of Heritage Sensitive LED Street Lighting | 01.11.2018 | 12.78 | Completed |
7.44
|
Total
|
88.29 | 64.95 |
Warangal (Telangana)
S.
No.
|
Name of the Project |
Sanction Date |
Amount released (in crore) |
Progress
Status (as on
31.03.2019)
|
UC
Received
till 31.03.2019
(in crore)
|
1
|
Bhadrakali Lake Foreshore Development | 14.10.2015 | 20.27 |
80%
progress
|
11.11 |
2
|
Development work at 1000 pillar temple area | 28.03.2016 |
0.18
|
Completed |
0.18
|
3
|
Development work at Kazipeth Dargah | 28.03.2016 |
1.78
|
Completed |
1.73
|
4
|
Rejuvenation of pond at Padmakshi Temple and Development of Jain Sites of Hanamkonda Hill |
28.03.2016 |
1.62
|
Completed |
1.62
|
5
|
Revival and Development of Fort Warangal | 14.10.2016 |
8.97
|
50%
progress
|
6.11
|
Total
|
32.82 | 20.75 |
The above statement was submitted by Ministry of Housing and Urban Affairs of undermentioned Lok Sabha Question:-
GOVERNMENT OF INDIA
MINISTRY OF HOUSING AND URBAN AFFAIRS
LOK SABHA
UNSTARRED QUESTION NO.1109
TO BE ANSWERED ON JUNE 27, 2019
PROJECTS UNDER HRIDAY
No. 1109 SHRI RAJESHBHAI CHUDASAMA
Will the Minister of HOUSING AND URBAN AFFAIRS be pleased to state:
- (a) whether it is a fact that only 52 per cent of the amount has been released to the State Governments by the Union Government for different projects under Heritage City Development and Augmentation Yojana(HRIDAY);
- (b) if so, the details thereof and the projects undertaken by the State Governments during each of the last three years, State-wise;
- (c) the status of the projects undertaken by the States till 31st March, 2019; and
- (d) the total amount utilized for each project during the said period, project-wise and State-wise?
ANSWER
THE MINISTER OF STATE (INDEPENDENT CHARGE) OF
THE MINISTRY OF
HOUSING AND URBAN AFFAIRS
(SHRI HARDEEP SINGH PURI)
As above
*****