Railways Amendment Act, 2008 : Quadrupling of Virar-Dahanu corridor on Western Railway, of MUTP III projects in District Palghar in the State of Maharashtra.

Railways Amendment Act, 2008 : Quadrupling of Virar-Dahanu corridor on Western Railway, of MUTP III projects in District Palghar in the State of Maharashtra.
Railways Amendment Act

MINISTRY OF RAILWAYS

(Western Railway) 

NOTIFICATION

Mumbai, the 28th August, 2020

Notification under Section 20A of the Railways Act, 1989

S.O. 3021(E).—In exercise of the powers conferred by sub-section (1) of section 20A of the Railways (Amendment) Act, 2008 (11 of 2008) and the Railways Act, 1989 (24 of 1989) (hereinafter referred to as the said Act). The Central Government, after being satisfied that for the public purpose, the land, the brief description of which has been given in the Schedule annexed hereto, is required  for execution of the Special Railway Project, namely, Quadrupling of Virar-Dahanu corridor on Western Railway, of MUTP III projects in District Palghar in the State of Maharashtra, hereby declares its intention to acquire such land;

[post_ads]

Any person interested in the said land may, within a period of thirty days from the date of publication of this notification in the Official Gazette, raise objection to the acquisition and use of such land for the aforesaid purpose under sub-section (1) of section 20D of the said Act;

Every such objection shall be made to the competent authority, namely Assistant Collector/Sub Divisional Officer, Dahanu, District Palghar, Maharashtra, in writing and shall set out the grounds thereof, and the competent authority shall give the objector an opportunity of being heard, either in person or by legal practitioner and may, after hearing all such objections and after making such further enquiry, if any, as the competent authority thinks necessary, by order, either allow or disallow the objections;

Any order made by the competent authority under sub-section (2) of section 20D of the said Act shall be final;

The land plans and other details of the land covered under this notification are available and can be inspected by the interested person at the aforesaid office of the competent authority.

[post_ads_2]

SCHEDULE

Brief description of the land to be acquired, with or without structure, for the Special Railway Project, namely, Quadrupling of Virar-Dahanu corridor on Western Railway, of MUTP III projects in Dahanu Taluka, District Palghar in the State of Maharashtra.

Sr.

No.

District

Taluka

Village

Survey No.

Area of Land to be Acquired in Hectare

1

Palghar

Dahanu

Vangaon

32A/1

0.29.04

32A1 A 2

0.12.04

32 A/3

0.01.44

32 E

0.37.24

81 A/1

0.00.85

7

0.34.19

23

0.49.32

[F.No. WNC 335/1 Vol. XVII]
VILAS S. WADEKAR, Chief Engineer (Construction) HQ