The details of New Line, Gauge Conversion and Doubling projects sanctioned from 2014 till date

NEW RAILWAY PROJECTS FOR WARDHA 

NEW+RAILWAY+PROJECTS+FOR+WARDHA

(a)  Year-wise details of new Railway lines laid in the country including Wardha, Maharashtra from 2014 till date are as under:-

YearNew Line commissioned (in KMs)Year wise Expenditure/Budget Allotment (` in Cr.)
2014-15
380
8433
2015-16
813
15828
2016-17
953
15987
2017-18
409.42
9032.8
2018-19313.60 (till Jan, 2019)13460( Budget allotment)
Further, Indian Railways does not run trains on State-wise basis as Railways cut across State boundaries. During 2014-15 to 2018- 2019(till 31st January, 2019) Indian Railways have introduced 885 train services of which 44 serve Wardha station.
(b)  228 New Line, Gauge Conversion and Doubling projects have been included in the Budget in the country including Wardha from 2014 till date.
(c)  The details of New Line, Gauge Conversion and Doubling projects sanctioned from 2014 till date are as under:-
SNPlan HeadName of ProjectsYear of

Inclusion
Length (in Km)Anticipa ted Cost (`in cr.)Outlay 2018-19

(`in cr.)
1
NLJeypore-Malkangir2016-171302343.64
95
2
NLJeypore-Nabarangpur2016-17
38
747.91150
3
NLChitra-Basukinath2016-17
37
859
20
4
NLMau-Ghazipur-Tarighat2015-16
51
1765.92200
5
NLBahraich-Shravasti- Balrampur/ Tulsipur2016-172105185.8
1
6
NLHaldibari-International Border2016-17
3
90
15
7
NLKatghora -Dongargarh2018-192955950
0.1
8
NLMorappur-Dharmapuri2016-17
36
360
1
9
NLIndore-Budhni2016-173425440
0.2
SNPlan HeadName of ProjectsYear of

Inclusion
Length (in Km)Anticipa ted Cost (`in cr.)Outlay 2018-19

(`in cr.)
10NLNimach-Badi Sadri2017-18
48
490.44
5
11NLSolapur-Tuljapur- Osmanabad (Umbrella Work)2018-19
80
953
Sanction ed in Umbrella work
12NLTalcher-Angul with ‘Y’ Connection at Talcher (Umbrella
Work)
2018-1914.48278.96
Sanction ed in Umbrella work
13NLTest track for RDSO2018-19
25
353.48
Sanction ed in Umbrella work
14NLDhule(Borbihir)-Nardana2018-1950.60492.76
Sanction ed in Umbrella work
15NLRameshwaram- Dhanushkodi2018-1917.2208.30
Sanction ed in Umbrella work
16NLChirmiri –Nagpur Halt2018-19
11
114
0.1
17GCPilibhit-Shahjahanpur2017-18
83
427
40
18GCGC of Ahmedabad- Mahesana for doubling2015-16
70
477289.3
19GCMathura-Vrindavan2017-18
11
98
0.1
20GCIndara-Dohrighat2016-17
34
213.35
10
21GCDabhoi-Chandod GC with extension upto Kevadiya2017-18
50
663
50
22GCKatosan Rd-Chanasma2017-18
52
313
0.1
23GCChanasma-Ranuj2017-18
13
85
0.1
24DLPune-Miraj-Londa2015-164673627.57435
25DLWardha-Ballarshah 3rd line2015-161321272.19
55
26DLItarsi- Nagpur 3rd line. Bal.2015-162802449.91105
27DLConstruction of 3rd line between Teegaon and Chichonda Ghat
section
2015-16
17
175.6635.25
28DLDaund-Manmad2016-172362081.27210
29DLManmad-Jalgaon 3rd line2016-171601035.16
52
30DLWardha-Nagpur 4th line2016-17
76
637.95
35
31DLJalgaon-Bhusawal 4th line2016-17
24
261.37
52
32DLVizianagram-Titlagarh (Sambalpur) 3rd line2015-16263.652336379
SNPlan HeadName of ProjectsYear of

Inclusion
Length (in Km)Anticipa ted Cost (`in cr.)Outlay 2018-19

(`in cr.)
33DL3rd & 4th line between Jarapaada- Budhapank with
flyover at Talcher.
2015-16
91
810120
34DL3rd & 4th line between Line between Budhapank- Salegaon
via Rajatgarh.
2015-161701173220
35DLKottavalasa-Koraput2015-161892500193
36DLKoraput-Singapur Rd.2015-161642362110
37DLByepass at Khurda Rd.,2015-161.61
25
11.91
38DLJagdalpur-Koraput doubling2015-161101547116
39DLRamna-Singrauli2015-161602436.21150
40DL3rd line bet. Patratu- Sonnagar (Dhanbad- Sonnagar )2015-162913406.16250
41DLHajipur-Bachwara2015-16
72
678.54260
42DLSamastipur – Darbhanga2015-16
38
491.01
50
43DLKiul- Gaya2015-161241200.2240
44DLBilli-Chopan (Renukut- Chopan)2015-167.8993.29
10
45DLKaraila Road- Shaktinagar section2015-1632.15528.57
5
46DLRanchi Road- Patratu section patch doubling.2015-16
31
348.2100
47DLAdditional bridge and doubling between Rampur
Dumra-Tal-Rajendrapul
2015-16
14
1491.47210
48DLKarota Patner-Mankatha surface triangle line2016-17
10
129.38
30
49DLSagauli-Valmikinagar2016-17109.71215.55
30
50DLGaya Byepass line for Manpur2016-17
2
29.52
1
51DLMuzaffarpur-Sagauli2016-17100.61185.74
40
52DLGarwa Road Rail over rail2016-17
10
262.71
1
53DLGomoh Flyover for down trains2016-17
15
487.73
50
54DLNimtita-Farakka (Sagardighi- Malda Town)2015-16
25
247.67
5
55DLJhansi-Bina 3rd line2015-161532001.63582
56DLByepass at Sainthia, Sitarampur, Mughalsarai, Allahabad,
Etawah
2015-16
35
830.73
2
SNPlan HeadName of ProjectsYear of

Inclusion
Length (in Km)Anticipa ted Cost (`in cr.)Outlay 2018-19

(`in cr.)
57DLMathura-Palwal 4th line2015-16
80
668.7150
58DLMathura-Jhansi 3rd line2015-162743677.76201
59DLJhansi-Khairar-Manikpur

& Khairar-Bhimsen
2016-174114187100
60DLYamuna Br.-Agra Fort With major Br at Yamuna river2016-17
2
121.58
10
61DLLalitpur-Birari with flyover at Lalitpur2016-17
16
304.44
10
62DL3rd Down line between Naini and Chheoki with additional
Platform
2017-18
2
25.13
8
63DL4th line between Bhaupur- Panki connecting Dn Loop of
Bhaupur to shunting neck of Panki.
2017-18
11
82
2
64DLAllahabad Division. Construction of Kanpur fly-over.2017-18
30
1790
0.1
65DLDoubling between New Coaching Complex and Kanpur2018-192.534.28
0.1
66DLProvision of 3rd line between Aligarh Jn – Daud Khan
parallel to UP line and construciton of flyover at Daudkhan
connecting DN loop line of Daudkhan to common loop of New
Daudkhan(DFC)
2018-196.9447.99
0.1
67DLProvision of 3rd line between Ruma Chakeri- Chandari in
connection with DFC
2018-1912.5176.68
0.1
68DLProvision of 4th line between from Chipiyana Buzurg to
Dadri connecting Down loop of Maripat and holding line of
Dadri in connection with DFC
2018-19
12
128.68
0.1
SNPlan HeadName of ProjectsYear of

Inclusion
Length (in Km)Anticipa ted Cost (`in cr.)Outlay 2018-19

(`in cr.)
69DLProvision of 4th line from Allahabad to Bumrauli flying
over at Subedarganj and connecting to UP loop of Bumrauli
2018-19
10
493.11
0.1
70DLProvision of chord line between Dailwara – Berari2018-195.250.24
0.1
71DLProvsion of flyover at Bhandai for Etawah bound down
trains.
2018-19
10
186.21
0.1
72DLGhazipur-Anurihar2014-15
40
197.73
75
73DLRosa-Sitapur Cantt-Burwal2015-16180.771306.42150
74DLBallia-Gazipur city doubling2015-1665.1447.56100
75DLDomingarh-GKP-GKP Cantt-Kusumhi2016-1721.15186.85
15
76DLBurhwal-Gonda 3rd line2016-1761.72714.34
10
77DLShahganj-Bhatni-Phephna- Indara, Mau-Sahaganj excl
Mau-Indara
2016-17150.281028.95
31
78DLBhatni-Aurnihar with RE excl Mau-Indara2016-17116.95600
40
79DLAurnihar-Jaunpur2016-17
60
366.71
38
80DLMalhaur-Daliganj doubling with electrification2017-18
13
110.94
5
81DLVaranasi-Madhosingh- Allahabad2015-16120750.56
75
82DLBongaigaon- Goalpara- Guwahati doubling2015-161762232300
83DLDigaru-Hojai doubling2015-16102871250
84DLNew Maynaguri- Gumanihat (remaining section)2016-1751.65612165
85DLAlamnagar-Utretia2015-16
20
132.66
63
86DLRajpura-Bhatinda2015-16172.641251.25400
87DLMuzaffarnagar – Tapri2015-1651.53376.7130
88DLBarabanki-Akbarpur2016-171611116.08
92
89DLJanghai-Pratapgarh- Amethi2016-17
87
700
39
90DLJaunpur-Tanda2016-17
94
676.3621.01
SNPlan HeadName of ProjectsYear of

Inclusion
Length (in Km)Anticipa ted Cost (`in cr.)Outlay 2018-19

(`in cr.)
91DLChord line between Jaunpur Jn. & Jaunpur city.2017-18
2
86.32
2.1
92DLJanghai-Phaphamau doubling with electrification2017-18
47
357.48
2.1
93DLAmristsar to Chheharta2018-19
7
28.68
0.1
94DLPhulera- Digana2015-16108.75686175
95DLDegana-Rai ka Bagh doubling2018-19145762
0.1
96DL3rd line of balance section bet. Kazipet -Ballarshah2015-162012063.03301
97DLDoubling bet. Gooty- Dharmavarm2015-1690.2636.38
76
98DLDoubling bet. Kalluru- Guntakal2015-16
41
323.0976.52
99DLDoubling of Secunderabad- Mehboobnagar2015-16
85
728.1250
100DLByepass at Renigunta, Dharmavaram, Wadi2015-16
21
273.0526.25
101DLByepass at Vijayawada, Kazipet2015-1630.15499.296.55
102DLVijaywada- Gudur 3rd line2015-162873548.68250
103DLGuntur-Guntakal2016-174433631.07200
104DL4th line bet.Jharsuguda- Bilaspur2015-162061973.66200
105DL3rd line bet. Pendra Road- Anuppur (Bilaspur- Anuppur)2015-1650.1393.98
50
106DL3rd line Anuppur-Katni2015-16165.521370.94175.04
107DLGevra Rd-Pendra Rd2015-161351900
0.2
108DLJharsuguda-Bilaspur — Flyover/Byepass (10 Km.)2015-16
10
299.65
10
109DLRajnandgaon-Nagpur 3rd line2015-162281908.51375
110DLBondamunda-Ranchi2015-16158.51724200
111DLRourkela-Jharsuguda 3rd line2015-16101970180
112DLKharagpur-Adityapur 3rd line2015-161321312115
SNPlan HeadName of ProjectsYear of

Inclusion
Length (in Km)Anticipa ted Cost (`in cr.)Outlay 2018-19

(`in cr.)
113DLMohishila – Kalipahari (Link) with 1 additional loop line
at MOH station
2015-16
5
43
18
114DLCKP-GOL 3rd line (34 Km)2015-16
34
355
72
115DLDamodar-Mohishila2016-17
8
76
32
116DLBondamunda-Rourkela 4th line2016-179.3
94
50
117DLConnections of DMF-LINK

“C” line with BZR Station.
2017-182.3
39
17
118DLTalgaria station to Bokaro N/ Cabin section in Adra
Division
2018-19
38
390.39
0.1
119DLPurulia-Kotshila doubling2018-19
36
338
0.1
120DLLink line between Lodhma and Piska bypassing Hatia/Ranchi
with Y connection
2018-1917.2428.65
0.1
121DLTrivandrum- Kanyakumari2015-1686.51432110
122DLMadurai- Maniyachi- Tuticorin2015-161601182
75
123DLManiyachi- Nagercoil2015-161021004
75
124DLNetravati-Mangalore2016-171.5
28
21
125DLSalem-Magnesite Junction-Omalur2017-18
11
115
5
126DLHotgi-Kudgi-Gadag2014-152841798400
127DLHubli-Chikjajur2015-161901141250
128DLArsikere-Tumkur2015-16
96
578100
129DLYelahanka-Penukonda2015-16121860120
130DLBaiyapannahalli to Hosur2018-19
48
375.67
0.1
131DLYeshwantpur to Channasandra2018-1921.7169.65
0.1
132DLPennukonda to Dharmavarm excluding Dharmavaram2018-1941.5294.67
0.1
133DL3rd line between Katni and Bina2015-16278.72478.23155
134DLGrade separator/Byepass at Katni.2015-1621.5582.13
75
135DLKatni- Singrauli doubling2015-162611762.94362
136DLItarasi-Jabalpur section: Patch doubling between
Sontalai-Bagra tawa stations.
2015-16
7
96.44
35
SNPlan HeadName of ProjectsYear of

Inclusion
Length (in Km)Anticipa ted Cost (`in cr.)Outlay 2018-19

(`in cr.)
137DLPowerkheda-Jujharpur single line flover in UP direction2016-17
12
247.0310.1
138DLJukehi chord line at Katni2016-170.5312.455.42
139DL4th line Vatwa- Ahmedabad- Sabarmati2015-1617.9231.43100
140DLSurendranagar-Rajkot2015-161161002.39250
141DLNimach-Chittaurgarh2015-16
56
389.99
75
142DLNagda-Ujjain – Doubling of Gambhir Bridge2016-170.4428.16
15
143DLIndore-Dewas-Ujjain2016-17
80
603.69
60
144DLAnand-Godhara2017-18
79
683
0.1
145DLSatna-Rewa doubling2015-16
50
403.4975.1
NL– New Line    GC– Gauge Conversion    DL– Doubling


The above statement was submitted by Ministry of Railways of undermentioned Lok Sabha Question:-

GOVERNMENT OF INDIA 
MINISTRY OF RAILWAYS 
LOK SABHA 
UNSTARRED QUESTION NO.1717 
TO BE ANSWERED ON 13.02.2019 
NEW RAILWAY PROJECTS FOR WARDHA 
1717. SHRI RAMDAS C. TADAS 
          SHRI CHANDRA PRAKASH JOSHI: 
Will the Minister of RAILWAYS be pleased to state: 
  • (a) the number of new railway tracks extended, the number of trains started and the amount spent in this regard in the country particularly in Wardha, Maharashtra since the year 2014 till date, year-wise; 
  • (b) the number of new projects announced since 2014 till date in the country particularly for Wardha; and 
  • (c) the number and details of projects out of these projects sanctioned and the budget allocation made in this regard? 
ANSWER 
MINISTER OF STATE IN THE MINISTRY OF RAILWAYS 
(SHRI RAJEN GOHAIN) 

(a) to (c)  Statement is laid on the Table of the House. 
STATEMENT REFERRED TO IN REPLY TO PARTS (a) TO (c) OF UNSTARRED QUESTION NO. 1717 BY SHRI RAMDAS C. TADAS AND SHRI CHANDRA PRAKASH JOSHI TO BE ANSWERED IN LOK SABHA ON 13.02.2019 REGARDING NEW RAILWAY PROJECTS FOR WARDHA
As above
******