1592. SHRI BHAGIRATH  CHOUDHARY:

Will the Minister of SOCIAL JUSTICE AND EMPOWERMENT be pleased to state:

(a) the selection procedure for comprehensive development of rural areas and for improvement in living standards of the villagers under Pradhan Mantri Adarsh Gram Yojana (PMAGY) in the country including the criteria fixed under it;

Pradhan Mantri Adarsh Gram Yojana

(b) the States where rural development works have been completed and villagers benefitted therefrom since its inception to December, 2021 including the amount spent/sanctioned, State-wise and year-wise;

(c) the details of works done so far in various Village Development Programmes (VDPs) in rural areas covered/benefitted thereunder in Rajasthan;

(d) the amount given, works approved/completed from 2019-20 to 2021-22, year-wise including districtwise list of selected villages; and

(e) whether villages have been benefitted with the completion of sanctioned works in Rajasthan under the said scheme during the last three years and if so, the details thereof, year-wise?

ANSWER
MINISTER OF STATE FOR SOCIAL JUSTICE AND EMPOWERMENT

(SHRI A. NARAYANASWAMY)

(a): Villages having a total population of 500 or more with more than 40% persons belonging to the Scheduled Castes are eligible for selection in the descending order of their SC population under the PMAGY scheme.

(b): Since the inception of the scheme till December 2021 (1252) villages completed all the works identified under the Village Development Plan. The year-wise details of funds released to the above States since inception to 2021-22 is at Annexure-I.

(c): In the State of Rajasthan, (2958) works have been so far completed in the selected villages. These works are mainly related to provision of drinking water, sanitation, internal roads, drainage, construction of Anganwadis, toilets in existing Anganwadis & Schools etc.

(d) & (e): The year-wise details of funds released to the State Government of Rajasthan for development of villages selected under PMAGY, along with the number of works approved and number of works completed in Rajasthan, which have benefited the said villagers during the last three years from 2019-20 to 2021-22, are as under:

Year

Amount released (Rs. In lakh)

Works approved

Works completed

2019-20

10379.00

2276

0

2020-21

1880.00

6168

0

2021-22

3690.54

392

(957) villages have been selected in Rajasthan from 2019-20 to 2021-22 for implementation of PMAGY and the district wise number of villages selected are at Annexure-11. The names of these villages are available on the scheme portal pmagv.gov.in.
Annexure-1
Annexure referred to in reply to Part-(b) of the Lok Sabha Unstarred Question No.tl592 dated 26.07.2022 asked by SHRI BHAGIRATH CHOUDHARY, Hon’ble MP regarding Pradhan Mantri Adarsh Gram Yojana

State-wise and year-wise details of funds released to States where development works have been completed

Name of State

Assam

Bihar

Chhattisgarh

Haryana

Himachal Pradesh

Rajasthan

Tamil Nadu

Year

2009-10

0.00

130.00

0.00

0.00

0.00

140.00

130.00

2010-11

1010.00

2142.50

0.00

0.00

2272.50

2132.50

2142.50

2011-12

1000.00

2250.00

0.00

0.00

2250.00

2250.00

2250.00

2012-13

0.00

0.00

0.00

0.00

0.00

0.00

0.00

2013-14

0.00

0.00

0.00

0.00

0.00

0.00

0.00

2014-15

0.00

0.00

0.00

120.00

0.00

0.00

0.00

2015-16

0.00

0.00

2100.00

0.00

0.00

0.00

0.00

2016-17

1575.00

0.00

2075.00

132.00

0.00

0.00

0.00

2017-18

0.00

0.00

375.00

0.00

0.00

0.00

0.00

2018-19

2850.20

3092.80

1400.20

1534.00

936.00

2995.00

2819.00

2019-20

904.60

3420.80

4582.00

633.60

3491.60

10379.00

2224.80

2020-21

1810.20

0.00

4008.00

2146.80

0.00

1880.00

0.00

2021-22

0.00

0.00

2198.80

0.00

1555.16

3690.54

14638.28

Annexure-11
Annexure referred to in reply to Part-(d) and (e) of the Lok Sabha Unstarred Question No.t1S92 dated 26.07.2022 asked by SHRI BHAGIRATH CHOUDHARY, Hon’ble  MP  regarding Pradhan Mantri Adarsh Gram Yojana

District wise list of selected villages from 2019-20 to 2021-22 in Rajasthan

SI. No.

Name of District

No. of villages covered

1.

Alwar

51

2.

Baran

OS

3.

Barmer

85

4.

Bharatpur

69

s.

Bhilwara

02

6.

Bikaner

44

7.

Bundi

11

8.

Chittorgarh

08

9.

Churn

32

10.

Dausa

51

11.

Dholpur

40

12.

Ganganagar

219

13.

Hanumangarh

40

14.

Jaipur

42

15.

Jaisalmer

09

16.

Jalore

13

17.

Jhalawar

10

18.

Jhunjhunu

03

19.

Jodhpur

34

20.

Karauli

57

21.

Kota

07

22.

Nagaur

27

23.

Pali

06

24.

Pratapgarh

04

25.

SawaiMadhopur

45

26.

Sirohi

23

27.

Tonk

20

Total

957


नोट :- हमारे वेबसाइट indiangovtscheme.com पर ऐसी जानकारी रोजाना आती रहती है, तो आप ऐसी ही सरकारी योजनाओं की जानकारी पाने के लिए हमारे वेबसाइट indiangovtscheme.com से जुड़े रहे।

*****

Pradhan Mantri Adarsh Gram Yojana

Brief Background
1. Scheduled Castes (SCs), who constitute 16.6% of our population as per 2011 Census, have historically suffered social and educational disabilities and economic deprivation arising there from. Accordingly, special provisions have been enshrined in the Constitution for advancement of their interests. These provisions range from measures to remove any kind of social disabilities imposed on them to ensure equality of opportunity in every sphere, to measures of positive discrimination to bring them on par with rest of the population.
Pradhan+mantri+adarsh+gram+yojana

2. Article 46 of Part IV (“Directive Principles of State Policy”) of the Constitution enjoins upon the State to promote with special care the educational and economic interests of the weaker sections of the people, in particular, of the Scheduled Castes and the Scheduled Tribes. Article 38 (2) in the same Part also enjoins upon the State to minimize inequities in income, and to endeavor to eliminate inequalities in status, facilities and opportunities, not only amongst individuals but also amongst groups of people residing in different areas or engaged in different vocations.

3. The Government has hence taken a number of initiatives for development of SCs, which have yielded positive outcomes, and have also resulted in narrowing the gap between the Scheduled Castes and the rest of the population. However, the focus of most welfare Schemes of SCs has been mainly cantered on individual beneficiaries rather than on the integrated development of SC pockets.
4. To enable an area based development approach, a new scheme called the Pradhan Mantri Adarsh Gram Yojana (PMAGY) was launched on a Pilot basis during 2009-10, following the Finance Minister’s declaration in his Budget Speech delivered on 6.7.2009. The Scheme aims at integrated development of villages in which the population of Scheduled Castes is above 50%. A total of 1000 villages from Tamil Nadu (225), Rajasthan (225), Bihar (225), Himachal Pradesh (225) and Assam (100) were selected for the Pilot phase.
5. During 2014-15, PMAGY was further extended (Phase-I) to cover another 1500 villages across 11 States namely Andhra Pradesh (7), Assam (75), Chhattisgarh (175), Jharkhand (100), Haryana (12), Karnataka (201), Madhya Pradesh (327), Odisha (175), Punjab (162), Telangana (6) and Uttar Pradesh (260).
Expansion of the Scheme:
6. In light of the benefits accruing to the residents of the villages through successful implementation of the Scheme, it has been decided to take up more villages in the Phase-II. All those districts are considered which have villages having total population ≥500 and with more than 50% persons belonging to the Scheduled Castes. Up to 10 such villages in descending order of SC population are proposed to be selected from each such district for implementation of the Scheme in this new Phase.
Revision of Scheme Guidelines:
7. To ensure all round development of the selected villages, so that they can indeed become ‘Adarsh Grams’, the said Scheme has been recently revised to capture the Gaps in critical socio-economic ‘Monitorable Indicators’ as part of various sectors/domains. These domains include water and sanitation, education, health and nutrition, agricultural best practices etc. amongst others.
New Approach for implementation:
8. The identification of needs or Gaps with regard to the ‘Monitor able Indicators’ will be based on a Need Assessment exercise. The ‘Village Development Plan’ (VDP) will be based on the data collected as part of the Need Assessment exercise. The Scheme relies heavily on convergence with other initiatives of the Central and State Governments for ensuring that the minimum infrastructure and critical services are made available to all the persons in the village, especially those belonging to the Scheduled Castes. PMAGY will provide the platform for convergent implementation of other Schemes with the aim to achieve saturation in the variousdomains. Whereas it is expected that the major portion of the funds requirement for implementation would be met from other Central or State Schemes, the ‘Gap-filling’ funds will be provided under the Scheme, for those areas which cannot be covered otherwise.
Funding under the Scheme:
9. For every new village selected, the Scheme provides for a total of Rs. 21 lakh of which Rs.20.00 lakh is for the ‘Gap-filling’ component and Rs.1.00 lakh is meant for ‘administrative expenses’ at the Centre, State, District and Village level in the ratio of 1:1:1:2. Initially, 50% of the admissible grant i.e. Rs.10.40 lakh per new village (including Rs. 10 lakh for ‘Gap-filling’ and Rs. 40, 000 for ‘administrative expenses’) will be released to the State Govt. either through PMAGY or through the infrastructure component of the Scheme of SCA to SCSP, or both. The remaining 50% of funds for the new villages would be released after due appraisal by the Central PMAGY Steering-cum-Monitoring Committee and only after reasonable physical and financial progress is achieved.
10. In addition to the newly selected villages, villages already implementing PMAGY in Phase-I will also receive an additional round of funding so that they are also able to achieve the desired goals for the socio- economic indicators now specified under the new Scheme Guidelines, provided they meet the revised eligibility criteria. For these villages, the Scheme provides for a total of Rs. 10 lakh of which Rs. 9.50 lakh is for the ‘Gap-filling’ component and Rs. 0.50 lakh is for ‘administrative expenses’ at the Centre, State, District and Village level in the ratio of 1:1:1:2.
11. Details of ‘funding’ and ‘flow of fund’ are explained at para-9 and 10 of the Scheme Guidelines. The State Government/UT Administration would initially release the funds to the District Administrations for, ‘administrative expenses’ i.e. for capacity building, awareness generation, preparation of the ‘Village Development Plans’ (VDPs) and initiating other non-cost based activities. The funds under the ‘Gap-filling’ component are to be released to the District Administration only after approval of the VDPs of the selected villages by the District PMAGY Convergence Committee and thereafter the District Administration can release funds to the Gram Panchayats or line departments for execution of the identified infrastructure works under VDP.
Project Monitoring:
12. The Scheme provides for setting up of various levels of Committees for guidance, monitoring and implementation. These Committees, especially the Convergence Committees at the Village, District and State levels, are crucial to the implementation as they would assess the requirements as well as plan and execute the works/services that are needed to be undertaken under various Schemes for the wholesome development of the villages. Selection of Villages under Phase-II of the Scheme and release of Fund:
13. The list of States/UTs in their descending order of their SC population as well as no. of villages eligible for funding under Phase-II as per revised norms of the scheme are as under:

Sl. No.
State
SC
Population
Ten village per district

taken under the Scheme under Phase-II
Fund Required (in Rs. Lakh)
Phase-INewTotalPhase-INewTotal
1
Uttar Pradesh413, 57, 608496757244901417514665
2
West Bengal214, 63, 2700210210044104410
3
Bihar165, 67, 3250348348073087308
4
Tamil Nadu144, 38, 4450271271056915691
5
Maharashtra132, 75, 8980145145030453045
6
Rajasthan122, 21, 5930288288060486048
7
Madhya Pradesh113, 42, 3206733340067069937663
8
Karnataka104, 74, 9922523926425050195269
9
Punjab88, 60, 1795716121857033813951
10
Andhra Pradesh84, 45, 3984991034020792119
11
Orissa71, 88, 4638319227583040324862
12
Telangana54, 09, 00051331385027932843
13
Haryana51, 13, 6151113714811028772987
14
Gujarat40, 74, 447025250525525
15
Jharkhand39, 85, 6444412917344027093149
16
Chhattisgarh32, 74, 2691012813810026882788
17
Kerala30,39,57301102121
18
Assam22, 31, 3213523827335049985348
19
Uttarakhand18, 92, 5160124124026042604
20
Himachal Pradesh17, 29, 25209090018901890
21
Jammu and Kashmir9, 24, 99107171014911491
22
Tripura6, 54, 918031310651651
23
Puducherry1, 96, 325010100210210
24
Manipur97, 328012120252252
25
Meghalaya17,35504408484
TOTAL
3904, 0944, 48439008597489874
14.  Fund Released under Phase-II of the Scheme:

Sl. No.
State

No of Villages for which fund released/being released
Fund Released/being releasedRemarks
Phase
-I
NewTotalPhase- INewTotal
1


Uttar Pradesh
37328365366.33411.23777.5SCA to SCSP*
2
West Bengal01051050.01092.01092.0&
3
Bihar01811810.01882.41882.4&
4
Tamil Nadu01441440.01497.61497.6PMAGY*
5
Maharashtra091910.0946.4946.4PMAGY*
6
Rajasthan01481480.01539.21539.2MCC
7


Madhya Pradesh
1802261872.02327.4MCC
46455.4MCC
8
Karnataka125

137
1300.0

1419.0
PMAGY*
12119.0SCA to SCSP*
9
Punjab76

110
790.4

1127.0
PMAGY*
34336.6SCA to SCSP#
10
Andhra Pradesh3535629.7551.2580.9SCA to SCSP*
11
Orissa5592147544.5956.81501.3SCA to SCSP*
12
Telangana5909549.5936.0985.5MCC
13
Haryana8859379.2884.0963.2
14
Gujarat025250.0260.0260.0PMAGY*
15
Jharkhand2379102227.7821.61049.3
16
Chhattisgarh7707769.3728.0797.3MCC
17
Kerala0110.010.410.4PMAGY*
18
Assam134

151
1393.6

1561.9
PMAGY*
17168.3SCA to SCSP**
19
Uttarakhand065650.0676.0676.0
20
Himachal Pradesh047470.0488.8488.8&
21
Jammu and Kashmir038380.0395.2395.2PMAGY*
22
Tripura026260.0270.4270.4SCA to SCSP*
23
Puducherry0550.052.052.0
24
Manipur012120.0124.8124.8PMAGY**
25
Meghalaya0440.041.641.6
TOTAL2472, 2042, 4512445.322921.625366.9

Progress of Pilot Phase:

15.  Physical and Financial Progress during Pilot Phase of the Scheme:





Sl



State


No. of selected villages

No of Works Approved

No of Works completed
No of Villages declared ‘Adarsh
Gram’

Total Fund Released (Rs. In Cr.)

UC
Submitted
1Assam10010020.1020.10
2Bihar225372131622345.22545.225
3Himachal Pradesh2254445.25545.15
4Rajasthan2251334-61127322545.25545.15
5Tamil Nadu22522545.22545.15
Total
1000617

Progress of Phase-I:

16.  Physical and Financial Progress during Phase-I of the Scheme:

Sl
State
No of Villages selected under Phase-I
By Dept.Under DiscretionRedistributedTotal
1
Assam75
75
2
Uttar Pradesh2001050
260
3
Madhya Pradesh2007750
327
4
Karnataka2001
201
5
Punjab1001250
162
6
Odisha10075
175
7
Jharkhand100
100
8
Chhattisgarh10075
175
9
Haryana12
12
10
Andhra Pradesh7
7
11
Telangana6
6
TOTAL
10751253001500

Sl
State
Central Assistance Released (Rs. Cr)Matching Share
14-1515-1616-1717-1818-19Total
1
Assam15.7515.75
2
Uttar Pradesh1.0042.001.108.651.8554.60
3
Madhya Pradesh7.7047.323.1510.5068.67
4
Karnataka0.1040.002.1142.21
5
Punjab18.703.501.3216.1039.625.60
6
Odisha21.0015.7536.75
7
Jharkhand21.0021.00
8
Chhattisgarh21.0020.753.7545.508.75
9
Haryana1.201.322.52
10
Andhra Pradesh0.700.771.47
11
Telangana0.600.661.26
Total30.00195.8262.6839.001.85329.3514.35

Sl


State
Physical and Financial Progress

Expendit ure

(Rs. Cr.)
No of VillagesVDP

Prepare d
Works Appd.
Works comple ted
Works in
Progres s
Villages declared
Adarsh Gram
1
Assam
75
68
58
0
58
0
0
2
Uttar Pradesh260
210
775
13
367
140
32.02
3
Madhya Pradesh327
251
2018
386
398
0
21.25
4
Karnataka201
199
102
0
78
0
40.10
5
Punjab162
105
677
101
557
0
21.09
6
Odisha175
0
0
0
0
0
0
7
Jharkhand100
100
1120
0
1120
0
0
8
Chhattisgarh175
175
2025
62
1857
0
41.75
9
Haryana
12
9
18
2
16
0
0
10
Andhra Pradesh
7
0
0
0
0
0
0
11
Telangana
6
0
0
0
0
0
0
Total
1500
1117
6793
564
4451
140
156.21

17. Financial Year wise releases are given below:

Year
Budget Allocation (Rs. In Crore)Expenditure (Rs. In Crore)
Up to 2013-14
–
201.00
2014-15
30.0030.00
2015-16
200.00195.82
2016-17
90.0062.68
2017-18
40.0039.00
2018-19
(Till 14-11-2018)
70.0065.94
Total
594.44
0 Shares